Construction Update: Slabs Down, Cores Rising

Highstreet Village construction site, late August 2026

Late August brought a milestone for Buildings 3 and 4. The west grade slab is poured, and the first structure has risen above it.

West grade slab poured and stripped, Buildings 3 and 4
The west deck, poured on August 15 and now stripped.

Progress this month

  • The west grade slab was poured on August 15. The formwork is stripped and the west deck is open.
  • Rebar on the Building 3 east deck is complete, and the slab edge is formed, inspected and ready to pour.
  • The Building 4 elevator core block wall is in, making it the first structure above the slab.
  • The P1 slab is stripped and re-shored, and patching and finishing are under way.
  • Electrical rough-in has started on P2.
  • Island curbs and the site access road at Cardinal Avenue are being finished.
Building 4 elevator core block wall rising above the slab
The Building 4 elevator core, the first structure above the slab.

Coming up

  • August 31: block work begins on the Building 3 elevator core
  • September 1 to 5: east grade slab pour for Building 3
  • September 8 to 19: core walls continue upward
  • Late September: main-floor forming starts above the grade slab

Building 6 is next

While Buildings 3 and 4 climb, Building 6 has broken ground. It is home to The Sunset Collection: studio to 3-bedroom condominiums, every home facing west, with The Nest and The Lookout amenities. Register for pricing and floor plans.