Late August brought a milestone for Buildings 3 and 4. The west grade slab is poured, and the first structure has risen above it.

Progress this month
- The west grade slab was poured on August 15. The formwork is stripped and the west deck is open.
- Rebar on the Building 3 east deck is complete, and the slab edge is formed, inspected and ready to pour.
- The Building 4 elevator core block wall is in, making it the first structure above the slab.
- The P1 slab is stripped and re-shored, and patching and finishing are under way.
- Electrical rough-in has started on P2.
- Island curbs and the site access road at Cardinal Avenue are being finished.

Coming up
- August 31: block work begins on the Building 3 elevator core
- September 1 to 5: east grade slab pour for Building 3
- September 8 to 19: core walls continue upward
- Late September: main-floor forming starts above the grade slab
Building 6 is next
While Buildings 3 and 4 climb, Building 6 has broken ground. It is home to The Sunset Collection: studio to 3-bedroom condominiums, every home facing west, with The Nest and The Lookout amenities. Register for pricing and floor plans.