Construction Update: Slabs Poured, Steel Rising

Highstreet Village Buildings 3 and 4 site, late July 2026

Here is where Buildings 3 and 4 stood at the end of July 2026. Crews are working across the parkade and grade-slab levels at the same time, and the structure is starting to take its final footprint.

West grade slab decking and steel, Buildings 3 and 4
West grade slab decking, with bottom steel going in.

Progress this month

  • West grade slab decking is complete, and the bottom steel is being installed.
  • Stripping of the P1 slab is mostly complete.
  • Concrete block infill has started in the parkade, and the storage room areas are being back-filled and compacted.
  • Electrical and plumbing knockouts are in place in the west deck.
  • Scaffolding is up on the east and west grade slabs.
  • The middle columns were poured on July 30, and the parkade ramp is formed and ready.
Parkade columns and ramp forming, Buildings 3 and 4
Columns poured and the ramp formed in the parkade.

Coming up

  • August 4: parkade ramp pour
  • August 7 to 10: conduit through the west grade slab
  • August 11 to 14: top steel on the west grade slab
  • August 28: target pour for the east grade slab

Buildings 1 and 2 are complete and home to residents. Buildings 3 and 4 are 100% sold out.

Building 6 is next

While Buildings 3 and 4 climb, Building 6 has broken ground. It is home to The Sunset Collection: studio to 3-bedroom condominiums, every home facing west, with The Nest and The Lookout amenities. Register for pricing and floor plans.