The wood framing is moving fast. As of October 8, 2026, Building 3 is three floors up and Building 4 is close behind.

Progress this month
- Building 3: the third-floor walls are nearly complete, and fourth-floor joisting starts on October 9.
- Building 4: the first two floors are framed and the corridor framing is in. Crews are now laying out the Level 3 walls.
- Masonry on the Building 4 elevator core is progressing.
- Plumbing and sprinkler stacks are following the framers on levels 1 and 2 of Building 3, with the A/C condensate lines connected.
- Crews are finishing the parkade lighting on west P2 and the equipment in the water entry room.
- Stripping of the formwork and scaffolding at ground level is wrapping up.

Coming up
- October 9: fourth-floor joisting at Building 3
- Ongoing: Level 3 framing at Building 4, plumbing and sprinkler stacks, and masonry on the Building 4 elevator core
Building 6 is next
While Buildings 3 and 4 climb, Building 6 has broken ground. It is home to The Sunset Collection: studio to 3-bedroom condominiums, every home facing west, with The Nest and The Lookout amenities. Register for pricing and floor plans.